The Case Against Mega Contracts in Mega Transit Projects

The Case Against Mega Contracts in Mega Transit Projects

October 01, 2021  | Paul Lewis

This article is focused on aspects of Eno’s latest report: Saving Time and Making Cents: A Blueprint for Building Transit Better. For more information about project delivery, register today for Eno’s Transit Cost and Delivery Symposium on October 18-21, 2021. At the event, we will share findings from Eno’s transit cost and delivery report, and include panel discussion on best practices in permitting reform and other project delivery themes among transportation professionals, policymakers, and researchers.


All types of transportation mega projects come with price tags that frequently run into the billions of dollars. This is particularly true for large rail transit projects, as we found in our database. $2.3 billion for the 4.3 mile extension of the Green Line in Boston. $1.7 billion for the 15-mile 1 Line in Seattle. $1.5 billion for the 6.6 mile second phase of the Expo line in Los Angeles. But just because a project can cost over $1 billion to build does not mean that it requires a multi-billion dollar mega contract. In fact, evidence from abroad suggests that breaking lines into smaller segments during contracting can bring significant cost savings.

In the United States, project sponsors often attempt to simplify projects by bundling its discrete elements into mega contracts. In theory, procuring an entire line or bundling tasks into one contract can have benefits. The management should be simpler with a single procurement, a single contract, and a single contractor with whom to coordinate activity.

In practice, projects abroad like the low-cost subway buildouts in Madrid or Santiago tend to break transit lines into sections of no more than 2 miles. They also tend to procure subway stations separately from tunneling contracts to acquire contractors with expertise in each specific task. Stakeholders and practitioners in these regions cite this unbundling as a critical means of keeping costs low. Their results back this up: underground transit costs in Madrid and Santiago average only $141 and $112 million per mile, respectively compared to over $500 million per mile in the United States.

Similar unbundling can be found in other countries, too. Rarely do international construction contracts exceed $300 million for transit lines. Our July report found rationale for breaking up a line into smaller sections is threefold.

First, it invites more competition. Few construction firms have the capacity or experience to handle a $1 billion project, so procurements end up with few bidders. On the other hand, many companies can handle a contract of $300 million or less. During the massive buildout of the subway system in Madrid from 1997-2003, using small contracts also helped build a domestic industry of construction firms that now do business all over the globe.

Unbundling also protects projects from disruption. Large mega projects frequently encounter unanticipated problems. A contractor could have underbid and found itself unable to cover its costs. Labor strife or poor work quality can halt construction. Disagreements over contractual terms can create work stoppages. But when transit lines are broken into segments, disputes only stop construction on a portion of the project while other segments proceed.

One of the starkest examples is the single $5.6 billion contract between Maryland and a construction consortium to build and operate the 16-mile Purple Line light rail system. Contract and change order disputes have all but stopped construction activities since 2020, which aren’t anticipated to resume until 2022. The line is now expected to open five years behind schedule and costs continue to balloon.

Breaking projects into smaller segments also provides agencies leverage. When dealing with a single contractor, an agency is beholden to it unless it wants the entire project stopped and have costs escalate. In our work, we found Santiago Metro has a policy where no two contractors are allowed to work on adjacent segments of a subway line, and no contractor can be awarded 2 segments of any given line. When a contractor has underperformed, project managers have simply cancelled the agreements and awarded the work to the other contractors that are working on adjacent segments.

The benefits of unbundling outweigh the potential benefits of a single, large contract. This is reflected in the successful delivery of complex transit lines abroad and has become standard practice in countries outside of the United States. Our report recommends that agencies should break up construction projects into manageable sections and cap contracts at no more than $300 million to $500 million.

However, breaking up construction contracts does not guarantee success on its own. Project sponsors must invest in the public sector staff and oversight needed to execute these smaller contracts strategically and clearly to ensure seamless interfacing and coordination. Doing so might require more management effort in the short run, but all evidence points to long term cost and timeline savings that make such efforts worthwhile.


For more information, register today for Eno’s Transit Cost and Delivery Symposium on October 18-21, 2021.

Share

Related Articles

Text of Debt Limit Bill NEPA Changes, Compared to Original GOP Bill

Text of Debt Limit Bill NEPA Changes, Compared to Original GOP Bill

This PDF document is the text of H.R. 1577, the BUILDER Act, introduced earlier this year by Rep. Garret Graves (R-LA), which was the GOP...

Supreme Court Downsizes

Supreme Court Downsizes "Wetlands" Scope of Clean Water Act

The U.S. Supreme Court on May 25 ruled that the Clean Water Act’s scope only applies to wetlands that have a “continuous surface...

Senate Clears Defense/Water/Coast Guard Bill After Rejecting Manchin Permitting Amendment

Senate Clears Defense/Water/Coast Guard Bill After Rejecting Manchin Permitting Amendment

Last night, the Senate voted to approve the 4,310-page legislative behemoth based on the national defense authorization bill (NDAA),...

Inflation Is Cutting into States’ Big Infrastructure Windfall

Inflation Is Cutting into States’ Big Infrastructure Windfall

“It’s still eating away slowly but surely,” said Jeff Davis, a senior fellow at the Eno Center for Transportation, a Washington,...

Shining More Lights on a Multi-Billion Dollar Problem: High Costs for Transit Construction

Shining More Lights on a Multi-Billion Dollar Problem: High Costs for Transit Construction

Eno and the NYU Marron Institute have been trying to answer similar questions. Marron Institute has been assessing “Why do...

Eno Attends White House Summit on Accelerating Infrastructure

Eno Attends White House Summit on Accelerating Infrastructure

What matters as much as $1 trillion in infrastructure spending? Making sure that money gets spent on time, on task, and on budget. Eno’s...

Eno Releases New Rail Transit Project Delivery Report

Eno Releases New Rail Transit Project Delivery Report

The Infrastructure Investment and Jobs Act (IIJA) provides public transportation programs with $90 billion in guaranteed funding over five...

Manchin Permitting Reforms Revealed; Senate Test Vote on Tuesday

Manchin Permitting Reforms Revealed; Senate Test Vote on Tuesday

Sen. Joe Manchin (D-WV) has finally released the text of his environmental permitting reform bill, which Congressional leaders have...

Webinar: On the Right Track: Rail Transit Project Delivery Around the World

Webinar: On the Right Track: Rail Transit Project Delivery Around the World

Eno’s newest study builds the ongoing initiative to improve transit rail project delivery in the United States. In On the Right Track, we...

Innovative ‘Transform 66 Outside the Beltway Project’ in Northern Virginia to Open on Time this Year

Innovative ‘Transform 66 Outside the Beltway Project’ in Northern Virginia to Open on Time this Year

As Jeff Davis, a Senior Fellow at the Eno Center for Transportation, recently noted: “If sustained highway cost inflation averages any...

Transportation May Be Left Out of Permitting Reform

Transportation May Be Left Out of Permitting Reform

As part of his deal with Democratic leaders to gain his support for the budget reconciliation bill, Senator Joe Manchin (D-WV) has also...

Tackling Governance in Transit Megaprojects – Key Lessons from Eno’s Examination of Transit Governance in Austin

Tackling Governance in Transit Megaprojects – Key Lessons from Eno’s Examination of Transit Governance in Austin

Over two dozen new rail transit projects are set to open for service across the United States by 2030. There will likely be even more...

Be Part of the Conversation
Sign up to receive news, events, publications, and course notifications.
No thanks