Field Hearing on California HSR Addresses Management Controls, Continued Commitment

Field Hearing on California HSR Addresses Management Controls, Continued Commitment

August 17, 2018  | Brianne Eby

August 16, 2018

Last Thursday (August 9), the House Subcommittee on Railroads, Pipelines, and Hazardous Materials met in California for a field hearing on the status of the state’s high-speed rail (HSR) project.

The hearing featured four witnesses: Calvin L. Scovel III, USDOT Inspector General; Brian Kelly, California High-Speed Rail Authority (CHSRA) CEO; Louis Thompson, California High-Speed Rail Peer Review Group Chairman; and Robbie Hunter, Building and Construction Trades Council of California President.

California established the California High Speed Rail Authority (CHSRA) in 1996 to plan for a possible HSR system connecting the major population and economic centers of the state, from San Francisco and Sacramento to San Diego. Since then, the project has seen fluctuating cost estimates and anticipated completion dates.

In his opening statement, subcommittee chairman Jeff Denham (R-CA) –­ whose district would be bisected by the trains – referred to the project as “the poster child for mismanagement.” Denham said that other pressing issues, such as the state’s water crisis, were more worthy of even a fraction of the money that has thus far been allocated to the HSR project.

With a new cost estimate that could reach $100 billion, which doesn’t include the originally planned legs of the project reaching Sacramento or San Diego, Denham claimed that if more tax dollars are going to be asked for, more information is needed about the state of finance and funding.

Focus on finances and funds

The project has struggled to reach a stable policy and financing framework amidst shifts in leadership. Per Proposition 1A, which was approved by Golden State voters in 2008 with 52.7 percent of the vote, the state was allowed to sell $9.95 billion in general obligation bonds, $9 billion of which was specifically allocated to HSR. Bond funds were only permitted for use on half the cost of the project, and CHSRA was required to seek private and additional public funds for all remaining costs.

The project received over $3.9 billion in federal appropriations in fiscal years 2009 and 2010 through the Federal Railroad Administration’s (FRA) High-Speed Intercity Passenger Rail (HSIPR) program. Most of that money was from the 2009 ARRA stimulus law, and per the use-it-or-lose-it requirements of ARRA, all of that money had to be expended by September 30, 2017. However, the $929 million in FY 2010 funding has yet to be spent.

The project has also received funding from the state’s cap-and-trade program in the form of a one-time $650 million amount in addition to variable quarterly amounts. The 2018 Business Plan for the project assumes annual receipts of $750 million from cap-and-trade. Though the state Legislature extended the cap-and-trade program’s length through 2030 when it passed Assembly Bill 398 in July 2017, the program’s ability to transfer funds to the HSR project was in jeopardy in the state’s primary election this past June with Proposition 70, which would have prevented CHSRA from borrowing against post-2023 cap-and-trade revenues. That measure failed.

Rep. Alan Lowenthal (D-CA), who served as the chair of the state Senate Transportation Committee when the bond issue came before voters, pointed to the discrepancy in the $9.95 billion in state bonds and $3.875 billion put forth by the federal government in the originally proposed plan. Proposition 1A was put before voters under the assumption that funding was to be split equally between the state government, federal government, and the private sector. Responding to this discrepancy, Kelly stated that the business plan allows CHSRA to build exactly what was originally proposed in Prop 1A, albeit in stages.

With regard to garnering private sector interest, Kelly stated that low-risk projects more easily attract investors. Currently, however, California is operating under a constrained funding program, and much of the project is still under environmental review. Once the project can demonstrate that it produces revenue, private money will be brought in, stated Kelly.

Of the federal and state money that has been received, only $4.6 billion has been spent while $18 billion remains unspent.

Streamlining environmental review

Addressing Kelly, chairman Denham inquired about the reasons for the delays to date and where CHSRA plans to come up with additional funding for the 2018 plan. Before Kelly could complete his response, Denham interjected with, “Is it labor? Has CEQA been a hold up? Are we done with the environmental review yet?”

Kelly pointed to requirements to quickly spend federal dollars, stating,  “we got into construction before we had all the right of way and third party agreements done. We will not repeat this process.” Denham again interrupted, asking what the state of California is doing itself, and how streamlining can be incorporated to speed the process.

Kelly indicated that the Authority has been trying for eight months to get National Environmental Policy Act (NEPA) responsibilities assigned to the state of California, which would help to move the process along more quickly. The project has ten segments and eight are still under environmental review.

Audit of FRA’s oversight

In 2017, Chairman Denham requested a federal audit to analyze whether necessary safeguards were in place to ensure that FRA’s HSIPR grants were allocated and expended appropriately.

The audit began in April of 2018, thus there were not yet conclusive findings to report at this hearing. Yet, Scovel reported that the FRA has taken steps to address the DOT-OIG’s recommendations, notably improving HSIPR project planning materials to include guidance to grantees on ridership forecasting, public benefit evaluations, and operating cost estimates.

When pressed on the roughly $1 billion gap in state matching funds needed to meet the $2.5 billion in federal dollars already spent, Scovel replied that CHSRA has until the end of 2022 to match.

Additionally, the audit is evaluating FRA’s oversight of grants to CHSRA. While the audit is currently underway, its objectives are to assess FRA’s 1) risk analysis, assessment, and mitigation efforts, and 2) procedures for determining whether Federal funds expended complied with Federal laws and regulations.

Preliminary findings from the oversight evaluation indicate that, among other things, FRA has updated its guidance on identifying and mitigating risks during grant amendment and adopted a grant-management staff-training program.

Next steps

Despite the tone of criticism set by chairman Denham’s opening statement, an optimistic outlook for the status of high-speed rail in California was present throughout the remainder of the hearing.

Rep. John Garamendi (D-CA), standing in for the ranking minority member of the subcommittee, highlighted that the project helped to bring an 18 percent unemployment rate in Stanislaus County down to 7 percent. In addition, an estimated $2 billion in economic activity has been already generated in the Central Valley, and roughly 500 Central Valley companies have been used as suppliers to the project.

The project has anticipated economic benefits, as well. Rep. Zoe Lofgren (D-CA) pointed to the opportunity for public-private partnerships as a means to raise revenue for construction and provide important housing and employment opportunities. Google has already announced plans for development at San Jose’s Diridon Station, which is expected to bring about 20,000 employees to downtown.

Share

Related Articles

Putting Climate into the Infrastructure Law

Putting Climate into the Infrastructure Law

Its single biggest investment category, however, is roads and bridges. Jeff Davis of the Eno Center for Transportation broke this...

White House Issues First Round of NEPA Regulation Re-Rewrites

White House Issues First Round of NEPA Regulation Re-Rewrites

This week, the Council on Environmental Quality (CEQ) issued the first of multiple forthcoming rules undoing changes made by the Trump...

How Can New Transit Environmental Review Approaches Help Address Climate Concerns?

How Can New Transit Environmental Review Approaches Help Address Climate Concerns?

This article is focused on aspects of Eno's latest report: Saving Time and Making Cents: A Blueprint for Building Transit Better. For...

Lawmakers vow action after Ida floods Gulf Coast, Northeast

Lawmakers vow action after Ida floods Gulf Coast, Northeast

But the bipartisan bill will be valuable in providing major investments in “future-proofing” infrastructure against climate change...

DeFazio looks to try again on his progressive transportation agenda

DeFazio looks to try again on his progressive transportation agenda

But Jeff Davis of the Eno Center said the Byrd rule will also require that every dime of the committee’s $60 billion be spent by...

The perverse reason it's easier to build new highways than new subways

The perverse reason it's easier to build new highways than new subways

“A transit agency is designed to operate transit, not build transit projects,” said Paul Lewis, the Eno Center’s director of policy....

Federal program to cut bus emissions gets a Senate mandate: Some buses must pollute

Federal program to cut bus emissions gets a Senate mandate: Some buses must pollute

Still, the five-year total of nearly $107 billion for transit was about 65% above what was expected if spending remained flat in that...

Op-Ed: Bipartisan Infrastructure Bill Could Be a Win for Climate, If it Can Be Leveraged to Those Ends

Op-Ed: Bipartisan Infrastructure Bill Could Be a Win for Climate, If it Can Be Leveraged to Those Ends

The newest assessment report from the Intergovernmental Panel on Climate Change, released this week, was depressing. Not that it contained...

Op-Ed: Incorporating Sustainability in Airport Planning

Op-Ed: Incorporating Sustainability in Airport Planning

Airports are a critical part of the U.S. transportation infrastructure as they play a key role in the economy and in connecting passengers...

Critics: 'big and bold' infrastructure bill falls short on helping states fight climate change

Critics: 'big and bold' infrastructure bill falls short on helping states fight climate change

It also includes $107 billion for transit, a 65% boost, according to an analysis by Jeff Davis, a senior fellow at the nonpartisan Eno...

Where does the infrastructure compromise deal leave EV charging?

Where does the infrastructure compromise deal leave EV charging?

“If a reconciliation bill emerges with 10 digits of guaranteed EV rebate money, that will go a long way towards reassuring...

Infrastructure bill's climate-change features face tricky path over money for electric cars

Infrastructure bill's climate-change features face tricky path over money for electric cars

“If a reconciliation bill emerges with 10 digits of guaranteed EV rebate money, that will go a long way towards reassuring automakers...

Be Part of the Conversation
Sign up to receive news, events, publications, and course notifications.
No thanks