California Auditor Questions Completion Timetable for High-Speed Rail Project

California Auditor Questions Completion Timetable for High-Speed Rail Project

November 16, 2018  | Jeff Davis

November 16, 2018

Yesterday, the California State Auditor released a new report critical of the state’s high-speed rail project. The report title itself was fairly damning: “California High‑Speed Rail Authority: Its Flawed Decision Making and Poor Contract Management Have Contributed to Billions in Cost Overruns and Delays in the System’s Construction.”

From a federal perspective, the key takeaway is this: the decision by the Obama Administration to dedicate use-it-or-lose-it ARRA stimulus money on a project that was not ready for construction, plus their highly unusual decision to allow a “tapered match” for the federal grants (whereby the state can spend 100 percent of the federal appropriation for a project jointly funded by the federal government and the state, with the state promising to pay its share later on, by a date certain) increasingly look like a bad idea. The report says:

The Authority began construction in the Central Valley in October 2013 despite being aware of the risks associated with beginning construction early—the fact that the Authority had not acquired sufficient land for building, had not determined how it would relocate utility systems, and had not obtained agreements with external stakeholders. These unmitigated risks have contributed to $600 million in cost overruns thus far for the three active Central Valley construction projects, with another $1.6 billion in additional costs needed to complete the projects. The Authority has cited the terms of a 2010 federal grant—which originally required construction to be complete by 2017—as the primary factor in its decision to begin construction when it did. However, we determined that even with a grant deadline extension until December 2022, the Authority could miss the new deadline unless Central Valley construction progresses twice as fast as it has to date. Missing the deadline could expose the State to the risk of having to pay back as much as $3.5 billion in federal funds.

To put that $3.5 billion and the “tapered match” in perspective, here are the total federal grants for the Central Valley segment of the California high-speed rail project and their required state matching shares, from the funding agreements on the CHSRA website:

 FRA Grant   CHSRA Match   Total 
FY09 ARRA  $ 2,552,556,231.00  $ 2,505,771,134.00  $ 5,058,327,365.00
50.46% 49.54%
FY10  $    928,620,000.00  $    359,805,000.00  $ 1,288,425,000.00
72.07% 27.93%
Total  $ 3,481,176,231.00  $ 2,865,576,134.00  $ 6,346,752,365.00
54.85% 45.15%

Under a normal federal funding grant that is approximately 50-50 as the FY09 ARRA grant was, the state/local partner has to put up one dollar of cash for every dollar of federal money as it is being spent. For a standard 80-20 highway grant, the state DOT has to put up one dollar of cash for every four dollars of federal funding, as the money is being spent.

But the tapered match agreement meant that every single dollar of that $2.55 billion has already been spent (ARRA had a hard deadline of September 30, 2017 for every single dollar to be outlaid, lest if vanish in a puff of smoke). Almost none of the state match of $2.505 billion has been spent yet. (The FY10 money has no legal deadline for expenditure, and the CHSRA funding schedule indicates that they plan to spend the federal FY10 money last, starting in July 2020 and ending in June 2023 .)

As the auditor’s report notes, the original ARRA grant required the state share to be spent alongside the federal share and be complete by September 30, 2017. But the grant agreement was later amended in December 2012 to allow the tapered match and then amended again in May 2016 to extend the deadline for completion of the Central Valley segment to December 31, 2022.  (See this May 2016 ETW article for more details.)

About that bit where the state may have to repay $3.5 billion if they can’t complete the Central Valley segment, as promised in the FRA funding agreements, by the end of 2022: this comes from a 2015 GAO letter stating:

If FRA determines the Authority has misused federal grant funds by, among other things, failing to make adequate progress on the project or otherwise failing to adhere to the terms of the Agreement, FRA may require the Authority to repay up to the entire amount of FRA funds paid under the Agreement. FRA also may seek repayment if the Authority fails to complete the project or one of its tasks under the Agreement, or if it fails to adhere to the [Funding Contribution Plan], or if FRA determines the Authority will be unable to meet its 50 percent share and complete the project on schedule. FRA can seek repayment either from the Authority or from the State of California because FRA’s repayment claim will constitute the collection of a claim of the U.S. Government under 31 U.S.C. Chapter 37, the basic statutory framework for collection of U.S. Government claims. Under this statute, FRA can recover its disbursements via an administrative offset against any funds payable by the U.S. Government to, or held by the U.S. Government for, the State of California.

(Emphasis added.)

This means that whoever is running the Federal Railroad Administration can simply refuse to amend the grant agreement further between now and December 2022 (there is a Presidential election intervening between now and then, of course) and potentially pick and choose $3.5 billion in other federal aid to California to cancel, if CHSRA can’t complete the Central Valley segment by that point. (The GAO letter does add the caveat that “It is uncertain whether the federal debt collection process has been used to recover funds of the magnitude potentially at issue under the Recovery Act Agreement.”)

Would FRA play hardball like that? Who knows.

Can California even finish the Central Valley segment by December 2022? This, also, is was questioned by the state auditor, and the answer appears to be: not at the rate they have been going. According to this chart in the auditor’s report, their current spending rates won’t finish the Central Valley segment until 2027:

And this is just talking about the Central Valley segment, which FRA and CHSRA picked in 2010 to start with because it was supposed to be the quickest, cheapest, easiest segment of the proposed system.

For the entire system, the auditor’s report also includes a good chart showing just how little money the state has actually identified to pay for the rest of the system:

Share

Related Articles

Biden, McCarthy Closing In On Debt Limit Deal As Time Runs Out

Biden, McCarthy Closing In On Debt Limit Deal As Time Runs Out

White House and Congressional negotiators are rumored to be close to a deal to increase the debt limit in exchange for spending reductions...

FY24 Appropriations Season Begins With Total Number Still Undecided

FY24 Appropriations Season Begins With Total Number Still Undecided

The House Appropriations Committee started the fiscal 2024 appropriations process this week, marking up bills in subcommittee that will be...

Debt Limit Talks Continue, Rescinding COVID Aid Still a Focus

Debt Limit Talks Continue, Rescinding COVID Aid Still a Focus

President Biden sat down with Congressional leaders on May 9 to discuss the pending need to increase the debt ceiling, talks which were...

House Passes Debt Ceiling Bill, 217-215

House Passes Debt Ceiling Bill, 217-215

The House of Representatives has passed the Republican debt ceiling bill (H.R. 2811), which provides a $1.5 trillion increase in the debt...

Cost of Last Year's Transportation-HUD Policies Rises by $16 Billion

Cost of Last Year's Transportation-HUD Policies Rises by $16 Billion

The Congressional Budget Office informally notified the House and Senate Appropriations Committees last week of their final estimate of...

McCarthy Introduces Debt Limit Bill Filled With Spending Cuts and Tax Credit Repeals

McCarthy Introduces Debt Limit Bill Filled With Spending Cuts and Tax Credit Repeals

After weeks of behind-the-scenes negotiations, House Speaker Kevin McCarthy (R-CA) this week introduced the text of legislation to increase...

Highway Construction Costs Have Risen 50% in Two Years

Highway Construction Costs Have Risen 50% in Two Years

The Federal Highway Administration recently released its updated index of highway construction costs for the July-September 2022 quarter,...

DOT Announces $296 Million in Bridge Grants

DOT Announces $296 Million in Bridge Grants

Most of Joe Biden's original proposal for an "American Jobs Plan" got downsized, or jettisoned outright, on the way to becoming the...

Transit's First

Transit's First "Fiscal Cliff" - The Fight for Operating Subsidies, Part 1

President Johnson and Congress established a program for giving financial aid for mass transit capital projects to localities in 1964. Ten...

Budget Would Make $13.5 Billion in Unfunded Promises for New Starts

Budget Would Make $13.5 Billion in Unfunded Promises for New Starts

President Biden's fiscal 2024 budget request proposes to incur $13.5 billion in unfunded promises for "New Start" mass transit systems, by...

California High-Speed Rail Project Wants 1/4 of All IIJA Rail Grant Money

California High-Speed Rail Project Wants 1/4 of All IIJA Rail Grant Money

This month, the California High Speed Rail Authority said that it needs $8 billion in federal grants under the Infrastructure Investment...

Budget Request is $6.3 Billion Below IIJA Authorized Level for FY24

Budget Request is $6.3 Billion Below IIJA Authorized Level for FY24

The most important thing to know about President Biden's fiscal 2024 budget request for transportation is that it does not make any changes...

Be Part of the Conversation
Sign up to receive news, events, publications, and course notifications.
No thanks